On 30 November 2026, phase 2 of Awaab's Law starts for social landlords in England. For anyone who runs repairs, the headline is simple: heating complaints now come with legal deadlines, and a missed deadline has to be explained with evidence.

Where the phases stand

Phase 1 came into force for the social rented sector on 27 October 2025. Phase 2 extends the requirements from 30 November 2026 to a further set of hazards: excess cold, excess heat, falls on the level, structural collapse, fire and explosions, electrical hazards, and domestic hygiene (including personal hygiene and food safety).

Phase 3 will extend the regulations to all remaining Housing Health and Safety Rating System hazards, apart from overcrowding. No date for phase 3 has been published, so treat it as planned rather than scheduled.

The detailed requirements are in the Hazards in Social Housing (Prescribed Requirements) (England) Regulations 2025, as amended in 2026. The landlord's defence, covered below, is in section 10A(5) of the Landlord and Tenant Act 1985.

What counts as an excess cold or excess heat hazard

The government's triage guidance describes excess cold as the extent to which a home can maintain an appropriate internal temperature. A significant hazard may include a home that cannot be adequately heated or kept at a safe temperature. A complete loss of heating during colder periods is given as an example of an emergency.

The guidance works through two cases that will feel familiar. An elderly tenant reports that their boiler has stopped working: that is treated as an emergency. A broken window handle, where the home can still be heated to some extent, is categorised as a significant excess cold hazard instead. The guidance also says that season should not on its own define how urgent a hazard is.

Excess heat covers threats to health from excessively high indoor temperatures. Awaab's Law does not apply to overheating caused solely by hot weather outside. It does apply where a defect in the home makes the effect of high outside temperatures worse. Faulty district heating that leaves a flat persistently hot is one of the guidance's examples of a significant hazard.

There are no temperature thresholds. The guidance says plainly that it does not set specific temperatures and expects professional judgement case by case. That puts weight on the reasoning you record at triage.

The clock

The timescales are the same as for other hazards in scope.

For an emergency hazard, the investigation and the relevant safety work must both be completed within 24 hours of the landlord becoming aware of it. Temporary measures count: the guidance gives "provide temporary heaters while fixing a boiler" as an example.

For a significant hazard, the landlord must investigate within 10 working days of becoming aware. Relevant safety work must then be done within 5 working days of the investigation concluding, counting from the day after it ends. Any supplementary preventative work, meaning work to stop the hazard coming back, must begin or steps must be taken to begin it within 5 working days. Where that is not possible, it must start as soon as reasonably practicable and within 12 weeks.

If the safety work cannot be completed in time, the landlord must secure suitable alternative accommodation for the household at its own expense, taking account of the household's needs, including disability or medical needs.

Take a boiler that fails in January in a flat where the tenant is in her eighties. That is an emergency on the guidance's own example. Within 24 hours you need someone out, the hazard made safe, and portable heaters in place if the part is on order. The permanent repair and anything that stops a repeat failure then follow the later deadlines.

The written summary

After every investigation, the tenant must receive a written summary within 3 working days of the investigation concluding. It must say:

  • whether a significant or emergency hazard was found, and what it is
  • what action is needed, with a target timeframe for beginning and completing it
  • or, if no action is needed under the Regulations, that this is the case and why
  • how to contact the landlord

Landlords must also keep the tenant updated on the timing and progress of the work.

What evidence to keep

Landlords have a defence if they can show they used all reasonable endeavours to comply. That defence depends on records. The guidance says landlords should keep clear records of all attempts to comply, should keep clear records of attempts to gain access, and should record advice given to tenants.

In practice, a defensible case file for a heating hazard would hold:

  • the date and route by which you became aware of the problem
  • the triage decision, with the reasons for treating it as emergency or significant
  • investigation date, findings and the written summary with its date of issue
  • every access attempt, including calls, letters and no-access visits
  • temporary measures supplied, and the dates of safety and preventative work
  • household circumstances you took into account, such as age or health

Disputes about compliance with Awaab's Law can go to the Housing Ombudsman once the landlord's complaints procedure has been used, and tenants can also go to court. Either way, the file is what you will be judged on. With phase 2 starting as winter arrives, check now that your repairs system time-stamps each step.

This is a summary, not legal advice; check the source documents linked below.

SenseCore keeps these case clocks and records in one place and flags what is due.

Sources

More posts
21 November 2026
Heat networks: registering with Ofgem before 26 January 2027
Existing heat networks must be registered with Ofgem by 26 January 2027. Who counts as operator or s…
21 November 2026
SECR and ESOS in 2026-27: what large organisations need to prepare
An ESOS progress update is due on 5 December 2026, Phase 4 qualification is fixed on 31 December 202…